NewsStocksSpaceX Plans More Than $74 Billion for Two AI Supercomputing Campuses

SpaceX Plans More Than $74 Billion for Two AI Supercomputing Campuses

Author: CryptoBriefing·

Key Takeaways

  • •SpaceX plans to spend more than $74 billion on two AI supercomputing campuses, allocating roughly $24 billion to Starbase, Texas, and about $50 billion to Cochise County, Arizona.
  • •The Starbase facility is designed to operate independently of the power grid, supported by a dedicated gas-fired plant expected to generate between 708 and 748 megawatts.
  • •The Arizona campus is planned for up to 6 gigawatts of capacity across nine buildings and will use dry cooling with no industrial groundwater consumption.
  • •Anthropic is reportedly the largest AI customer, contributing roughly one-third of that segment's revenue, while Google has agreed to pay $920 million per month for computing services.
  • •Both projects still require local approval, with tax abatement votes and a public hearing scheduled for December 9, 2026.
SpaceX Plans More Than $74 Billion for Two AI Supercomputing Campuses

SpaceX built its name launching rockets, but its latest spending plan targets something far more earthbound: servers. The company said on November 12, 2026, that it plans to invest more than $74 billion across two artificial intelligence supercomputing campuses.

Around $24 billion is slated for Starbase, the company's Texas headquarters, while about $50 billion is headed to a second campus in Cochise County, Arizona. The timing matters because AI is no longer a side project at SpaceX — the segment is reportedly where most of the company's money now comes from.

Two campuses, two very different designs

Each location reflects a different answer to the same underlying challenge: supplying enough power for large-scale AI hardware. Power availability has emerged as one of the central constraints in building AI infrastructure, making the two sites' contrasting approaches to electricity a distinguishing feature of the plan. The Texas project is the smaller of the two. The Starbase supercomputing center is designed to run independently of the power grid, supported by its own gas-fired power plant on a 444-acre site. That plant is expected to generate between 708 and 748 megawatts — a fraction of the capacity planned for Arizona.

The Starbase project is projected to create more than 3,000 construction jobs and over 500 permanent positions. SpaceX is also dedicating $220 million to local water infrastructure tied to the site.

Arizona is where the scale expands considerably. The Cochise County campus will span roughly 747 acres and carry a capacity of up to 6 gigawatts — equivalent to 6,000 megawatts, or roughly eight times the top end of the Texas plant's planned output — spread across nine buildings. Unlike Starbase, the Arizona site is expected to eventually connect to local electric cooperatives rather than relying on dedicated on-site generation. It is also designed around dry cooling methods, with no planned industrial groundwater use. Dry cooling, which dissipates heat with air rather than water, is a design choice commonly used where water resources are limited.

The Arizona campus is anticipated to bring approximately 5,500 construction jobs and 1,000 permanent jobs. Taken together, the two sites are projected to generate roughly 8,500 construction jobs and around 1,500 permanent positions.

Why a rocket company wants this much compute

The investment makes more sense in light of where SpaceX's revenue is reportedly coming from. The AI segment accounted for more than half of the company's revenue in the third quarter of 2026. The demand side reflects a broader industry pattern: as AI labs scale up model training and deployment, securing large blocks of computing capacity has become a central operational priority.

Anthropic, the AI lab behind the Claude models, is reportedly the largest customer, contributing roughly one-third of that revenue. Google has also signed on, agreeing to pay $920 million per month for computing services. At that monthly rate, the Google deal alone works out to more than $11 billion over a full year.

The shift also coincides with SpaceX's move into public markets. The company listed under the ticker SPCX in June 2026, which means its spending decisions now face scrutiny from shareholders in a way they never did when it was private.

The approvals still have to land

None of this is a done deal yet. Both projects still require local approvals, and votes on tax abatements — arrangements in which local governments reduce or waive certain taxes, typically in exchange for investment and job creation — are scheduled for December 9, 2026, alongside a public hearing covering both facilities. Neither project can move forward until those local decisions are made.

What this means

For SPCX shareholders, the plan is a clear signal about where management sees growth. Committing more than $74 billion to AI infrastructure suggests SpaceX views compute as a core business, not a temporary windfall.

That conviction cuts both ways. The reported revenue concentration is notable: with Anthropic alone contributing roughly one-third of AI revenue, the health of a few large customer relationships carries outsized weight. The Google agreement adds a second heavyweight.

The power strategy is arguably the most distinctive part of the plan. Texas goes fully off-grid with its own gas-fired plant, while Arizona eventually plugs into local electric cooperatives. Rural Cochise County in particular could see a significant economic shift if the full 6-gigawatt buildout materializes.

The near-term item to watch is the December 9 vote on the tax abatements.

Disclosure: This article was originally published by CryptoBriefing and edited by Diego Almada Lopez.