PM Modi, Nepal PM Balendra Shah Lay Foundation Stone for SJVN's 669 MW Lower Arun Hydropower Project in Nepal
Key Takeaways
- •Indian Prime Minister Narendra Modi and Nepal's Prime Minister Balendra Shah jointly laid the foundation stone for the 669 MW Lower Arun Hydroelectric Project during a virtual ceremony held from New Delhi.
- •The ₹5,792.36 crore project on the Arun River in Nepal's Sankhuwasabha and Bhojpur districts is projected to produce roughly 2,901 million units of electricity annually at a tentative tariff of ₹4.99 per unit.
- •Lower Arun will run in tandem with SJVN's upstream 900 MW Arun-3 project, using its discharged water to generate additional renewable energy without building a separate storage reservoir.
- •Under the Project Development Agreement, Nepal's government will receive 21% of the electricity generated free of cost, along with tax and royalty revenue and foreign exchange benefits from cross-border energy trade.
- •SJVN secured the project through international competitive bidding in January 2021, signed the Project Development Agreement in June 2023, and has begun construction with commissioning targeted for FY 2030-31.

India's state-owned power producer SJVN Ltd said on Monday, November 23, that the foundation stone of its 669 MW Lower Arun Hydroelectric Project in Nepal was jointly laid by Indian Prime Minister Narendra Modi and Nepal's Prime Minister Balendra Shah during a virtual ceremony held from New Delhi. The joint participation of both heads of government underscored the project's place within India-Nepal cross-border energy cooperation.
The cross-border hydropower initiative carries an estimated cost of ₹5,792.36 crore and is expected to generate approximately 2,901 million units of electricity annually. It will rely on a tandem operating system with SJVN's upstream facility to maximise renewable output without building a new storage reservoir, while supplying a significant share of free power to Nepal alongside broader regional economic benefits.
Developer, Location and Key Terms
The project is coming up on the Arun River in Nepal's Sankhuwasabha and Bhojpur districts. It is being developed by SJVN Lower Arun Power Development Company Pvt Ltd (SLPDC), a wholly owned subsidiary of SJVN. The project carries a tentative tariff of ₹4.99 per unit, and commissioning is targeted for the financial year 2030-31.
SJVN is a Navratna public sector enterprise under India's Ministry of Power, incorporated as a joint venture between the Government of India and the Government of Himachal Pradesh. The Lower Arun assignment adds to the company's cross-border hydropower portfolio, which includes the 900 MW Arun-3 project in Nepal.
Ceremony at the Project Site
An event was organised at the Lower Arun project site to mark the foundation stone laying. Attendees included project employees and representatives of Nepal's Ministry of Energy, the Investment Board of Nepal and the District Coordination Committee, along with local government leaders — among them the mayor and the Gaon Palika Pramukh — ward representatives, the District Forest Department, Community Forest User Groups and local residents.
SJVN Chairman and Managing Director Bhupender Gupta thanked the Prime Ministers of India and Nepal for their guidance and for the confidence placed in the company as a development partner. He also acknowledged the support of India's Ministry of Power, the Ministry of External Affairs and other ministries of both countries in securing the clearances and approvals required for the project.
Integration With Arun-3 and Project Design
A key feature of the Lower Arun project is its integration with SJVN's 900 MW Arun-3 Hydroelectric Project, located upstream on the same river. Both projects will operate under a tandem operation system, under which water discharged from Arun-3 will be used to generate electricity at Lower Arun. Taken together, the two developments place 1,569 MW of SJVN-developed capacity along the Arun River.
The arrangement is designed to optimise the use of available water resources and enable additional renewable energy generation without the construction of a separate storage reservoir.
The Lower Arun project will comprise four generating units of 167.25 MW each, a 17.4-km head race tunnel and a surface powerhouse. It is being developed on a Build, Own, Operate and Transfer (BOOT) basis. Major construction packages have already been awarded, and construction activities are underway.
Benefits for Nepal and Local Communities
Under the Project Development Agreement, 21% of the electricity generated by the project will be provided free of cost to the Government of Nepal. The project is also expected to contribute to Nepal's revenue through applicable taxes and royalties, while supporting foreign exchange earnings through cross-border energy trade. Nepal's benefits are therefore structured across several parallel channels — free electricity, government revenue and foreign exchange — rather than a single stream.
The project is expected to create direct and indirect employment opportunities during both the construction and operational phases. Development activities are also expected to generate business opportunities and support local economic growth in the Sankhuwasabha and Bhojpur districts.
Local area development initiatives will include the construction and upgradation of schools, healthcare facilities, drinking water supply systems and other essential community infrastructure. These initiatives are expected to support socio-economic development, improve the quality of life of local communities and promote entrepreneurship and regional economic activity.
Award History and Agreements
The Government of Nepal awarded the 669 MW Lower Arun Hydroelectric Project to SJVN through international competitive bidding on January 29, 2021. SJVN subsequently signed a Memorandum of Understanding with the Investment Board of Nepal on July 11, 2021. The Project Development Agreement was signed on June 1, 2023, in the presence of the Prime Ministers of India and Nepal. From competitive award to foundation stone, the project has moved through successive milestones over multiple years; with construction already underway, the next key marker is the targeted commissioning in FY 2030-31.
SJVN Shares on the BSE
In Monday trading, shares of SJVN Ltd ended at ₹54.91 on the BSE, down ₹0.88, or 1.58%.