Nigeria's new spectrum plan aims to boost internet access, but inflated right-of-way fees could stall it
Key Takeaways
- •NCC data shows Nigerians consumed 1.731 million terabytes of data in September 2026, with monthly mobile data usage rising more than threefold from 518,000 terabytes in January 2023 to 1.66 million terabytes in July 2026.
- •The NCC's Incentive-Based Spectrum Investment Framework, still a proposal in consultation, aims to tie spectrum incentives to verifiable infrastructure investment, but the paper itself states spectrum alone cannot resolve congestion without parallel investment in fibre backhaul, cell sites and reliable power.
- •5G population coverage stood at just 13% as of April 2026 and the technology accounted for only 5% of network share by September 2026, leaving most connections on older network generations.
- •Thirteen years after the 2013 agreement to fix Right of Way fees at ₦145 per linear metre, 12 states charge nothing, 16 charge the benchmark and nine charge above it, while states including Adamawa, Enugu and Ekiti layer application fees on top, reaching ₦700,000 in Ekiti.
- •Roughly 80-85% of Nigeria's fibre-to-the-home deployment is concentrated in cities such as Lagos, Rivers and FCT Abuja, as high fees and permitting costs lead operators to prioritise densely populated, higher-return locations over rural areas.

Nigeria's internet consumption is growing faster than telecom operators can expand their networks, even as the country's digital economy accelerates. Data published by the Nigerian Communications Commission (NCC) shows that Nigerians consumed 1.731 million terabytes of data in September 2026, and that monthly mobile data consumption rose more than threefold, from 518,000 terabytes in January 2023 to 1.66 million terabytes in July 2026.
That growth has not translated into a better experience for users. While internet penetration and data revenue keep climbing, the quality of experience continues to fall, leaving many Nigerians struggling to secure a good connection when speeds drop, particularly in congested locations or at night.
The regulator's spectrum proposal
In its consultation paper on the Incentive-Based Spectrum Investment Framework (IBSIF), the NCC acknowledges that current network infrastructure is struggling to keep pace. The regulator wants the framework to provide a structured approach for linking appropriate spectrum-related incentives to additional, verifiable infrastructure investment. Issued as a consultation paper, the IBSIF remains at the proposal stage rather than settled policy.
The scale of the shortfall is evident in the numbers. 5G population coverage stood at just 13% as of April 2026, and the technology accounted for only 5% of network share as of September 2026, leaving the overwhelming majority of connections on older network generations. Urban centres are battling chronic network congestion, while rural and unserved communities receive service that falls below appropriate coverage, capacity and quality thresholds — a widening gap between data demand and the networks that carry it.
Why spectrum alone will not fix the problem
Linking spectrum incentives to verifiable infrastructure rollouts appears logical on paper, but the IBSIF does not, by itself, resolve the challenges keeping network quality below par. Nigerian telecoms face severe structural realities, with a major bottleneck around inflated Right of Way (RoW) fees — the levies operators pay states to run fibre ducts along roads and other public pathways — coupled with hidden application and permitting costs.
The consultation paper itself concedes that meeting rising data demand requires increased parallel investment in fibre backhaul, new cell sites and reliable power. It adds that in areas where traffic growth is outpacing network capacity, investment in site densification, modernisation, fibre and supporting infrastructure can reduce congestion and improve reliability. The clear implication is that spectrum investment alone is not enough to meet rising demand — it is only one of several challenges facing the Nigerian telecoms industry. Without deep fibre-optic networks carrying data from cell towers to core networks, additional spectrum addresses only a minimal share of the problem rather than resolving it.
The right-of-way bottleneck
Although operators are expected to commit more to infrastructure investment, laying fibre across Nigerian states remains one of the sector's most stubborn challenges. The federal government has yet to achieve a uniform RoW price of ₦145 per linear metre across all states. At one point, the government lobbied state governors to adopt a ₦0 rate in a bid to fast-track fibre-optic rollout, and by 2025–2026, one-third of the states — 12 governors — had waived RoW charges entirely. Yet several states still charge more than the agreed rate, or have rebranded the levy as expensive application costs.
The trend continued this week. On Monday, Ekiti State, in its Right of Way Law, 2026, fixed the maximum RoW fee at ₦145 per linear metre for ducts and cables and ₦700,000 per site for a Base Transceiver Station — a move that further highlights the bottlenecks telcos face in deploying infrastructure and expanding internet access.
Data from the NCC's Ease of Doing Business portal shows that, out of Nigeria's 36 states and the Federal Capital Territory, 12 states currently charge zero RoW fees, while 16 states charge exactly ₦145 per linear metre. Nine states, however, charge above the threshold — 13 years after the national agreement, reached in 2013, to fix RoW fees at ₦145 per linear metre.
Hidden fees weigh on fibre deployment
Attention has increasingly turned to the hidden fees associated with fibre deployment. Some states charge application fees even where the RoW levy is ₦0 or ₦145. Both Adamawa and Enugu collect application fees of ₦100,000 despite having zero RoW charges. Ekiti collects the highest at ₦700,000, even though its new Right of Way Law pegs duct and cable fees at the federal benchmark of ₦145 per linear metre. Others include Cross River (₦250,000), Edo (₦10,000), Gombe (₦10,000), Lagos (₦20,000), Ondo (₦20,000), Oyo (₦50,000) and Yobe (₦25,000).
Beyond the decision to invest in and upgrade infrastructure, Nigerian operators face rigorous application processes and hidden fees while laying fibre ducts. Under those conditions, operators mostly prefer to deploy fibre in industrialised areas and concentrated cities where they can earn the highest returns. Deployments in rural and semi-urban areas carry the lowest immediate return on investment, and where high RoW fees and hidden permitting costs inflate infrastructure costs in those areas, operators prioritise highly populated locations.
That dynamic helps explain why roughly 80-85% of Nigeria's fibre-to-the-home deployment is concentrated in top cities such as Lagos, Rivers and FCT Abuja — a pattern that underscores the digital divide as rural areas continue to search for reliable internet coverage.
What needs to change
Spectrum policy cannot operate alone. Federal and state authorities need to enforce uniform RoW charges, eliminate hidden application fees and curb multiple taxation on telecom infrastructure. Thirteen years after the ₦145 agreement, reported charges for fibre rollout across states still range from ₦6,600 to ₦700,000. Without those fixes, Nigeria's ambition to provide quality network access nationwide will remain largely unmet. The near-term markers to watch are how the NCC settles the IBSIF following the consultation process, and whether the nine states still charging above ₦145 — and those layering high application fees on top — align with the federal benchmark.