Endeavour Mining Approves $1.2 Billion Assafou Gold Mine in Côte d'Ivoire as Costs Climb 13%
Key Takeaways
- •Endeavour Mining approved a $1.2 billion construction budget for the Assafou gold project in Côte d'Ivoire, roughly 13% higher than the April feasibility study estimate, with first production targeted for the first half of 2029.
- •Assafou is expected to produce an average of 320,000 oz of gold annually over its first eight years at all-in sustaining costs of $1,026 per ounce, and together with the Sabodala-Massawa underground expansion supports a target of 1.5 million oz of annual production by 2030.
- •The budget rose by $139 million, with higher land and crop compensation accounting for about 60% of the increase, and the company has committed $58.7 million to date.
- •Endeavour's shares dropped 8.1% to £37.94 in London on Thursday, while processing at the suspended Mana mine in Burkina Faso is now expected to resume in the second quarter of 2027, later than analysts had forecast.
- •Record free cash flow of $1.02 billion through September, up 50% year over year, combined with $263 million in net cash, strengthens the company's ability to finance the project.

Endeavour Mining (LSE, TSX: EDV) has taken the investment decision to build its Assafou gold project in Côte d'Ivoire, approving a construction budget of $1.2 billion (C$1.7 billion) — roughly 13% above the estimate in April's feasibility study — with first production targeted for the first half of 2029.
Shares in the company traded 8.1% lower at £37.94 in London on Thursday afternoon, valuing Endeavour at about £9 billion ($11.9 billion). Separately, the company said processing at its suspended Mana mine in Burkina Faso is expected to resume in the second quarter of 2027, later than National Bank had forecast.
"Overall, we view the quarter positively on earnings, cost containment and cash conversion, although the timeline for a restart at Mana may be longer than what is currently implied by consensus estimates," National Bank mining analyst Mohamed Sidibé wrote on Thursday.
Assafou and an underground expansion at the Sabodala-Massawa mine in Senegal form the basis of Endeavour's goal of producing 1.5 million oz. of gold annually by 2030. At its planned average rate of 320,000 oz. per year, Assafou alone would account for roughly a fifth of that target. The approval comes as record cash generation strengthens the company's capacity to fund growth, while operational setbacks limit near-term output.
Higher compensation
Assafou's budget has risen by $139 million from the $1.06 billion outlined in the feasibility study released April 23. Higher land and crop compensation accounts for roughly 60% of the increase, power infrastructure allowances make up 10%, and operational preparations and additional contingency contribute 15% each.
Costs for the power connection and the final routing of a national highway diversion remain under negotiation. Endeavour said the terms of the project's mining convention have been agreed in principle with Côte d'Ivoire, with signing expected in the coming weeks. Alongside those open infrastructure negotiations, the convention signing is one of the near-term items to track as construction mobilizes.
Located about 280 km northeast of Abidjan, Assafou is expected to produce an average of 320,000 oz. of gold annually during its first eight years at all-in sustaining costs (AISC) of $1,026 per ounce — well below the $1,866-per-ounce group average recorded through September. The cost estimate assumes a gold price of $2,500 an ounce, below the $3,000-per-ounce basis for the company's current guidance. The feasibility study envisages a 16-year mine life and a processing plant with an annual capacity of 5 million tonnes.
Lycopodium has been awarded the engineering, procurement and construction management contract. Resettlement earthworks are scheduled to begin late this month and plant earthworks before year-end, followed by concrete work in the second quarter of 2027 and commissioning in early 2029. Construction of power, tailings and water-storage facilities is expected to start early next year, with mine pre-stripping in 2028. Endeavour is weighing contractor mining against operating its own fleet, a decision that remains outstanding. The company has committed $58.7 million so far, about 5% of the revised budget, with spending set to accelerate this quarter.
Endeavour is also evaluating more than 20 exploration targets within 10 km of Assafou. Its 2026–2030 program targets another 1 million to 1.5 million oz. of resources across the Tanda-Iguela property.
Mana weighs
Underground mining at Mana was suspended on Oct. 28 after part of an access ramp subsided. Restart plans remain subject to geotechnical work and regulatory approval, with processing to follow the resumption of mining and the rebuilding of stockpiles.
Sidibé had anticipated a restart in the first quarter of 2027. He now considers roughly 90,000 oz. a reasonable preliminary production estimate for Mana next year, compared with consensus of 158,000 oz. He said that shortfall could reduce consensus forecasts for group free cash flow by about $160 million, or 6%.
Endeavour maintained its 2026 production guidance of 1.09 million to 1.265 million oz., with output expected in the lower half of the range. Production through September fell 10% to 820,000 oz., at an AISC of $1,866 per ounce. The company also reaffirmed AISC guidance of $1,600 to $1,800 per oz., based on a gold price of $3,000 an ounce. Excluding the additional royalties associated with higher gold prices, nine-month costs stand at about $1,700 an ounce, Endeavour said.
Cash funds growth
Free cash flow reached a record $1.02 billion through September, up 50% from a year earlier — a nine-month figure equating to roughly 85% of Assafou's revised budget. Endeavour ended the quarter with $263 million in net cash after reducing gross debt by $412 million, and had returned $312 million to shareholders through dividends and buybacks as of Nov. 10.
Third-quarter adjusted earnings of $1 per share exceeded the 77¢ consensus cited by BMO Capital Markets. Stronger production at Lafigué contributed, but BMO mining analyst Raj Ray said in a note that the earnings beat largely reflected lower taxes and a smaller share of earnings attributable to minority shareholders.
At Sabodala-Massawa, Endeavour is targeting first underground development ore before year-end and commercial production in early 2028. Delivery of that first ore would mark the opening step of the expansion that, alongside Assafou, anchors the 2030 target.