Philippine DoE Expects Semirara Mining to Meet Existing Coal Mine Obligations Amid New Bidding Round
Key Takeaways
- •Energy Secretary Sharon S. Garin said Semirara Mining and Power Corp. must complete all deliverables under its current contract even if it chooses not to bid for a new operating agreement.
- •SMPC has operated the Semirara coal mine in Antique province for nearly five decades, with its existing contract set to expire in July 2027.
- •The DoE relaunched its coal bidding round covering three areas with combined estimated reserves of 207 million metric tons, including SMPC's flagship Semirara mine.
- •SMPC has raised concerns about provisions requiring asset inventory disclosure and relying solely on financial offers to rank qualified bidders.
- •The DoE aims to sign coal operating contracts with winning bidders by Jan. 13, 2027, and is gathering stakeholder feedback to refine the bidding guidelines.

The Philippine Department of Energy (DoE) expects Consunji-led Semirara Mining and Power Corp. (SMPC) to fulfill its existing contractual obligations at the country's largest coal mine as the government prepares to award new coal operating contracts.
Energy Secretary Sharon S. Garin said the company remains responsible for meeting its commitments under the current contract, regardless of whether it participates in the bidding for a new operating agreement.
"The developer is obligated to fulfill the contract and complete all the deliverables stipulated under it," Ms. Garin told reporters last week. "But I don't think Semirara will abandon the project because they have a responsibility," she added.
SMPC has operated the Semirara coal mine in Antique province for nearly five decades. Its existing coal operating contract is set to expire in July 2027.
The company has raised concerns over certain provisions of the government's coal bidding rules, particularly requirements involving the disclosure of asset inventories and the turnover of certain assets, as well as the use of financial offers as the sole basis for ranking qualified bidders.
The DoE recently relaunched its coal bidding round, offering three predetermined areas with combined estimated coal reserves of 207 million metric tons. Among the areas on offer is the Semirara mine, SMPC's flagship asset and the country's largest coal-producing operation. Because the Semirara mine itself is on offer, the bidding will determine who holds the operating contract once SMPC's existing agreement expires.
According to Ms. Garin, the requirement for incumbent operators to disclose their asset inventories is intended to give prospective bidders sufficient information about the mining areas.
"Because to be fair to the possible bidders, they have to know what's in store and what they're bidding. What's the asset there? What's the potential? What's the resource?" she said. "We need to give as much details to ensure transparency. If there's no equipment, then we have to say it. If there is, then we have to say it," she added.
The department is seeking additional feedback from stakeholders to address concerns and further refine the bidding guidelines, Ms. Garin said. How those guidelines are revised in response, and whether SMPC ultimately joins the bidding, will be the key developments to follow.
The DoE is targeting the signing of coal operating contracts with the winning bidders by Jan. 13, 2027, ahead of the expiration of SMPC's existing agreement.
— Sheldeen Joy Talavera
Source: BusinessWorld