TEPCO Delays Second Reactor Restart at Japan's Kashiwazaki-Kariwa Nuclear Plant
Key Takeaways
- •TEPCO delayed the restart of Unit 7 at the Kashiwazaki-Kariwa nuclear plant after identifying a problem with the strength of the concrete structure housing the reactor in September.
- •TEPCO must revise both the construction plan and restart schedule to comply with Japanese counter-terrorism requirements that mandate the facility withstand a deliberate plane crash.
- •The Unit 7 restart had been targeted for August 2029, but the contractor building the reactor housing said the date could slip by more than one year.
- •The delay could increase Japan's gas demand over the near and medium term, as utilities may boost spot LNG purchases now that elevated electricity prices have made gas-fired generation profitable again.
- •Earlier this year TEPCO restarted Unit 6, the first reactor at Kashiwazaki-Kariwa to return to service nearly 15 years after the Fukushima disaster, with the site totaling nearly 8 GW of capacity.

Tokyo Electric Power Company (TEPCO) will delay the restart of a second reactor at its Kashiwazaki-Kariwa nuclear power plant in Niigata prefecture, Japan — the largest nuclear facility in the world by nameplate capacity — after identifying a problem with construction at the site.
TEPCO, which also operated the Fukushima nuclear power plant before the 2011 disaster, has planned for years to bring Kashiwazaki-Kariwa back into service. Earlier this year, the company restarted Unit 6, the first reactor at the plant to return to operation, restoring nuclear power generation at the facility nearly 15 years after the Fukushima disaster. The site has a total nameplate capacity of nearly 8 gigawatts (GW), a scale that makes its gradual return a significant piece of Japan's post-Fukushima nuclear restart.
Nuclear energy accounted for roughly 30% of Japan's electricity mix before the Fukushima meltdown in 2011. The disaster prompted the closure of all reactors for safety checks. Since 2015, Japan has restarted 15 of its 33 reactors, while 7 more are in the process of receiving restart approval — leaving the majority of the country's reactor fleet still offline.
TEPCO had planned to bring a second reactor at the site, Unit 7, online by August 2029. In September, however, the company identified a problem with the strength of the concrete structure that will house the reactor. TEPCO must now revise both the construction plan and the restart schedule for Unit 7 to comply with counter-terrorism requirements set by Japan's nuclear safety watchdog, which mandate that the facility be built strong enough to withstand a deliberate plane crash.
Takeyuki Inagaki, superintendent of the Kashiwazaki-Kariwa nuclear power station, told a media briefing on Thursday that it was too early to provide a revised timeline. He noted, however, that the contractor responsible for building the reactor housing structure had said the August 2029 restart date could slip by more than one year.
"It will take time to determine the cause," Inagaki said, as carried by Bloomberg.
Delays in nuclear reactor restarts could lift Japan's gas demand over the near and medium term. In the coming weeks, Japanese utilities may increase spot purchases of LNG cargoes, as surging electricity prices in recent days have made gas-fired power generation profitable for the first time since the Iran war began. For Japan's nuclear restart — and its fuel demand outlook — what to watch next is how quickly TEPCO finalizes its revised construction plan for Unit 7, and whether the August 2029 target slips by more than one year, as the contractor has indicated it could.
By Tsvetana Paraskova for OilPrice.com.